In waiting line theory, number of customers waiting in the queue is referred to as
Official theoretical question paper for Operation Research (OEC-CS701A) conducted by Maulana Abul Kalam Azad University of Technology. All questions from Groups A, B, and C are reproduced below with marks weightings.
In waiting line theory, number of customers waiting in the queue is referred to as
For finding an optimum solution in transportation problem _____ method is used.
In PERT, the maximum time that is required to perform the activity under extremely bad conditions is known as
A game is said to be fair if the value of the game is
In North-west corner method, first allocation is made at
The assignment problem always form a _____ matrix.
The difference between the maximum time available and the actual time needed to perform an activity is known as
When all the players of the game follow their optimal strategies, then the expected pay-off of the game is called
Traffic intensity in Queuing theory is also called
An assignment problem is considered as a particular case of
'Buffer Stock' is
Solve the following LPP using graphical method: Maximize Z = 3x₁ + 2x₂; Subject to x₁ ≤ 4; 2x₂ ≤ 12; 3x₁ + 2x₂ ≤ 18; x₁ ≥ 0; x₂ ≥ 0.
A small maintenance project consists of the following jobs whose precedence relationships with duration (days) are given below: | Jobs | 1-2 | 1-3 | 2-3 | 2-5 | 3-4 | 3-6 | 4-5 | 4-6 | 5-6 | 6-7 | | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | | Days | 15 | 15 | 3 | 5 | 8 | 12 | 1 | 14 | 3 | 14 | Find the critical path and total project duration.
Find the saddle point and optimal strategies having the following pay-off matrix: | | B1 | B2 | B3 | | :--- | :--- | :--- | :--- | | A1 | 10 | 2 | 3 | | A2 | 7 | 6 | 8 | | A3 | 0 | 3 | 1 |
Draw a network diagram for the following project. Find critical path and project duration. | Activity | A | B | C | D | E | F | G | H | I | J | K | L | M | | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | | Predecessor | - | A | B | A | D | E | - | G, J, H | - | A, C, K | I, L | - | - | | Duration (days) | 6 | 4 | 7 | 2 | 4 | 10 | 2 | 10 | 6 | 13 | 9 | 3 | 5 |
Solve the LPP by graphical method Maximize Z = 3x₁ + 2x₂ Subject to 2x₁ + x₂ ≤ 2 3x₁ + 4x₂ ≥ 12 x₁, x₂ ≥ 0
Find the critical path for the following problem. The following table shows the jobs of a network along with their time estimates (in days). | Job | 1-2 | 1-6 | 2-9 | 2-4 | 3-5 | 4-5 | 5-8 | 6-7 | 7-8 | | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | :--- | | to | 3 | 2 | 6 | 2 | 5 | 3 | 1 | 3 | 4 | | tm | 6 | 5 | 12 | 5 | 11 | 6 | 4 | 9 | 9 | | tp | 15 | 14 | 30 | 8 | 17 | 15 | 7 | 27 | 28 | i) Draw the project network. ii) Find the critical path. iii) Find the probability that the project is completed in 31 days.
Solve the following assignment problem using Hungarian method. | | M1 | M2 | M3 | M4 | | :--- | :--- | :--- | :--- | :--- | | J₁ | 1 | 4 | 6 | 3 | | J₂ | 9 | 7 | 10 | 9 | | J₃ | 4 | 5 | 11 | 7 | | J₄ | 8 | 7 | 8 | 5 |
Solve the following LPP by Simplex method Maximize Z = 60x₁ + 50x₂ x₁ + 2x₂ ≤ 40 3x₁ + 2x₂ ≤ 60; x₁, x₂ ≥ 0
Solve the following LPP by Simplex method Minimize Z = 4x₁ + 8x₂ + 3x₃ x₁ + x₂ ≥ 2 2x₁ + x₃ ≥ 5; x₁, x₂, x₃ ≥ 0
Solve the following transportation problem using VAM method, check optimality using MODI method and find the optimal solution. | Destination | D₁ | D₂ | D₃ | Supply | | :--- | :--- | :--- | :--- | :--- | | S₁ | 10 | 7 | 8 | 45 | | S₂ | 15 | 12 | 9 | 15 | | S₃ | 7 | 8 | 12 | 40 | | Demand | 25 | 55 | 20 | |