In queuing system, ________ refers to those waiting in a queue or receiving service.
Official theoretical question paper for Operation Research (OEC-CS701A) conducted by Maulana Abul Kalam Azad University of Technology. All questions from Groups A, B, and C are reproduced below with marks weightings.
In queuing system, ________ refers to those waiting in a queue or receiving service.
When the total demand is equal to the total supply then the transportation problem is said to be:
An activity that does not consume neither any resource nor time is known as:
A matrix which shows the gains and losses resulting from moves and counter moves is called:
A queue is formed when the demand for a service:
LPP involving four variables can be solved by:
An activity is said to be critical activity if:
The position in the pay-off matrix where the minimax coincides with the maximin is called:
Commonly assumed probability distribution of customer arrival pattern in a queue is:
To find initial basic feasible solution of transportation problem the difference of smallest cost and next higher cost of each row and column is related to:
What is expected time value in a PERT problem with to, tm, and tp as 6, 10 and 14 days respectively?
In a ________, the amount won by all the winners together is equal to the sum of the amounts lost by all the losers together.
Construct a network for each of the activities and their precedence relationships are given below: | Activities | A | B | C | D | E | F | G | | --- | --- | --- | --- | --- | --- | --- | --- | | Predecessor | --- | --- | A | A | B | C | D,E |
Apply maximin and minimax principle to solve the game whose pay-off matrix is given below: | | B1 | B2 | B3 | B4 | | --- | --- | --- | --- | --- | | A1 | -5 | 2 | 1 | 6 | | A2 | 5 | 6 | 4 | 8 | | A3 | 4 | 0 | 1 | -3 |
In a public telephone booth the arrivals are on average 15 per hour. A call on the average takes 3 minute. If there is just one phone, find the proportion of the time the booth is expected to be idle.
Show that the vectors (1,2,3) and (4, -2,7) are linearly independent.
For the following network, find the critical path and the expected time to complete the project. 
Details of a small project are given below. i) Draw a network diagram for this project. Find the critical path, the expected project completion time. ii) What project duration will have 95% confidence of completion? [Given, P(Z ≤ 1.64) = 0.95] | Activity | Most Likely | Optimistic | Pessimistic | Immediate Predecessor | | --- | --- | --- | --- | --- | | A | 3 | 1 | 7 | — | | B | 6 | 2 | 14 | A | | C | 3 | 3 | 3 | A | | D | 10 | 4 | 22 | B, C | | E | 7 | 3 | 15 | B | | F | 5 | 2 | 14 | D, E | | G | 4 | 4 | 4 | D |
Solve the following pay-off matrix; determine the optimal strategies and the value of the game | | B | | --- | --- | | A | 5 1 | | | 3 4 |
(a) A two channel waiting line with Poisson arrival has a mean arrival rate of 50 per hour and exponential service with a mean service rate of 75 per hour for each channel. Find the probability that an arrival in the system will have to wait. (b) An ice-cream company sells one of its types of ice-cream by weight. If the product is not sold on the day it prepared, it can be sold at a loss of 50 paisa per pound. But there is an unlimited market for one day ice-cream. On the otherhand, the company makes a profit of Rs. 3.20 on every pond of ice-cream sold on the day it is prepared. The past daily orders form a distribution f(x) = 0.2 - 0.0002x, 0 ≤ x ≤ 100. How many pound of ice-cream should the company prepare every day?
Solve the Assignment problem for minimum cost. | Men\Machine | A | B | C | D | | --- | --- | --- | --- | --- | | M1 | 18 | 26 | 17 | 11 | | M2 | 13 | 28 | 14 | 26 | | M3 | 38 | 19 | 18 | 15 | | M4 | 19 | 26 | 24 | 10 |
Solve the following rectangular game by graphical method. | Player A | 1 0 4 1 | | --- | --- | | | -1 1 -2 5 |