Define material management. State its objective.
Official theoretical question paper for Introduction To Industrial Management (HSMC-501) conducted by Maulana Abul Kalam Azad University of Technology. All questions from Groups A, B, and C are reproduced below with marks weightings.
Define material management. State its objective.
What is Master Scheduling?
State advantage of value analysis.
Define ERP.
Define Organization.
The expected time (Tₑ) of a PERT activity in terms of optimistic time (Tₒ), pessimistic (Tₚ) and most likely time (Tₘ) is given by ____________
What is Economic Order Quantity? State its formula.
What are the phases of PPC?
What are unnecessary cost in value engineering?
What is supply chain management?
Difference between "strike" and "lockout".
Define critical path in network diagram.
What are the five phases of value engineering?
State the benefits and demerits of JIT production system.
Differentiate between "Line organization" and "Functional Organization".
Define the term (a) Events (b) Activity (c) Critical activity (d) Non Critical activity (e) Dummy activity
Explain Organizational culture and climate in detail.
The ABC manufacturing company requires 1250 components per month throughout the year for manufacturing electronic equipment. If ordering cost is Rs. 50 per order, unit cost is Rs.5.00 per component and annual inventory carrying cost are 10%, Find EOQ. If the company decides to operate with a back order inventory policy then taking back order cost to be Rs. 7.50 per unit per year, find revised EOQ.
What are the main element of Production Planning and Control? Explain in details.
Explain value analysis procedure. State the conditions in which value analysis must be applied.
Draw and explain ERP cycle. State its merits and demerits.
Write short note on 1. Value engineering 2. Test for value analysis 3. Stages in value analysis