Retrieving academic index assets...
Makaut
HomePYQsTests
Pricing
Sign Up
Makaut

The premier academic archive for MAKAUT students, providing curated previous year questions, solutions, and official syllabus resources.

Get the Mobile App
GET IT ONGoogle Play
Download on theApp Store
Download from Indus App Store
Platform
  • Home
  • PYQs
  • Question Papers
  • Viva Questions
  • Important Questions
  • Syllabus
  • Academic Tools
  • Pricing
  • Blog
Guidelines
  • Disclaimer
  • Community Guidelines
Company
  • About
  • Contact
  • FAQ
Legal
  • Privacy Policy
  • Terms of Service
  • Refund Policy
  • Cookie Policy
  • Subscription Policy
© 2026 MAKAUT Study Dev Hub. All rights reserved.
Platform version: v1.0.0
Home/PYQs/Sem 7/Project Management And Entrepreneurship/2024
HSMC701Sem 7 • 2024 Exam
Full Marks: 70 • Time: 3 Hours

MAKAUT Project Management And Entrepreneurship 2024 Question Paper

Official theoretical question paper for Project Management And Entrepreneurship (HSMC701) conducted by Maulana Abul Kalam Azad University of Technology. All questions from Groups A, B, and C are reproduced below with marks weightings.

Download MAKAUT Project Management And Entrepreneurship 2024 Question Paper PDFView All HSMC701 Papers

AGroup A — Objective / Multiple Choice Questions

10 × 1 = 10 Marks
1(i)[1 Mark]

Activities P, Q, and R instantly follow activity M, and their current starting times are 12, 19, and 10. So, what is the latest finishing time for activity M?

1(ii)[1 Mark]

Define bar chart.

1(iii)[1 Mark]

What is an Event?

1(iv)[1 Mark]

Bar chart was invented by whom?

1(v)[1 Mark]

What do you mean by Audit of a project?

1(vi)[1 Mark]

CPM stands for ________.

1(vii)[1 Mark]

What do you mean by Capital of a business?

1(viii)[1 Mark]

What is a BAR Chart?

1(ix)[1 Mark]

What is post project audit?

1(x)[1 Mark]

Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finishing time for the three activities are 12, 15, and 10, then what will be the earliest starting time for Y?

1(xi)[1 Mark]

NSTC means ________.

1(xii)[1 Mark]

SSI stands for ________.

BGroup B — Short Answer Conceptual Questions

3 × 5 = 15 Marks
2[5 Marks]

Explain various phases of Capital Budgeting.

3[5 Marks]

Write a short note on Organization Breakdown Structure (OBS).

4[5 Marks]

What do you mean by feasibility of a Project? How the feasibility study is conducted before starting a project.

5[5 Marks]

How entrepreneurship involves the development of small scale industries. – Explain.

6[5 Marks]

Explain the concept of zero defects.

CGroup C — Long Answer Analytical & Numerical Questions

3 × 15 = 45 Marks
7(a)[5 Marks]

What do you mean by PERT Analysis and CPM in respect of project management techniques?

7(b)[5 Marks]

How one can identify the Critical Path and its significance? Explain with an example and diagram.

7(c)[5 Marks]

Explain The Dummy Activity with Reference To Network Analysis.

8(a)[5 Marks]

What do you mean by entrepreneurship?

8(b)[5 Marks]

Explain various risk mitigation strategies for a firm.

8(c)[5 Marks]

What is divergent and convergent thinking?

9(a)[10 Marks]

Define WBS? Explain with an example the development of work breakdown structure in project management.

9(b)[5 Marks]

What is Blue Ocean strategy?

10(a)[8 Marks]

Explain the motivational theory of McClelland and what do you mean by sustainable competitive advantage?

10(b)[7 Marks]

Explain in detail various risk mitigation strategies for a firm.

11(a)[8 Marks]

Explain with an example the development of work breakdown structure in project management.

11(b)[7 Marks]

Explain how various project ideas are generated?